Combined-cycle power plant PGU-TES-52
PGU-TES-52 MW is designed to generate electrical and thermal energy by burning natural gas.
Application
Main equipment:
- four gas turbine units GTA-8RM with a unit rated electrical power of 8 MW with generators of the GTG-8-2RUHL3 type;
- four double-circuit steam-water recovery boilers with a unit steam output of 20 t/h and a heat output of a gas water heater of 5 Gcal/hour
- two steam turbine units T-8.5/10.2-3.4/0.18 with an electrical power of about 8.5 MW in heating mode and about 10 MW in condensing mode with steam water condensers, with T- type generators 12-2У3;
- gas booster compressor station DKKS 9000-3/3-22 consisting of three containerized natural gas booster compressor units
- four-section wet-type fan cooling tower.